Gaston School District Bond Update September 28, 2017 Gaston School District is well into the bond project. School has begun and we continue to watch improvements take place each day. Current Progress:

  • Demolition of buildings (9 total) took place this past summer as planned.
  • Grading and partial parking lot completion took place summer of 2017. The rest of the parking lot and sidewalks will be completed summer of 2018 when the bond project is completed.
  • The temporary cafeteria is completed and functioning well for the district. It is locaated in the "old covered play area" at the elementary school.
  • District office is temporarily located in the former high school library.
  • The new covered play area is completed with basketball hoops being installed in spring of 2018.
  • The existing high school science lab was remodeled to house up to 24 students.
  • The weight room was moved and is being remodeled so that it functions at a greater and safer capacity.
  • The new building is being constructed. We see footings and cement work being completed each day. It will be completed in the summer of 2018.

Click here to see the latest plans!